Clock In
Use the Clock In screen to clock in an employee for their shift. When a shop employee arrives for the day, he or she must log in (or clock in) to the handheld device to report his or her arrival for that day.
...
Start Indirect starts an indirect labor activity. Note.
Note: You must be “Clocked In” to access this menu item, if not clocked in, you will be automatically redirected to the Clock In form.
Processing Steps:
Enter or search for a resource group ID.
Enter or search for an indirect code that belongs to that resource group.
Click START INDIRECT to start it and add it to the work queue.
View the Work Queue or continue adding Activities.
Select the Indirect Activity
The end activity screen allows the user to set the activity complete once the job has been finalised. Entering the full qty will automatically set the Complete flag.
...
Start Production is used to enter job operation information for a production activity.
Note: You must be “Clocked In” to access this menu item, if not clocked in, you will be automatically redirected to the Clock In form.
Processing Steps:
Enter the job number, assembly sequence and operation sequence.
If the number and sequences are valid, it will automatically load the job details. You can override the Resource group and/or Resource.
Click START PRODUCTION to start the production and add it to the work queue. Or you can add more production operations to the work queue.
Once in the work queue you can select the operation to complete by selecting within the rectangular border of the operation and clicking END ACTIVITY option button.
The end activity screen then allows the user to enter the qty and other relevant information such as PCID, Lot Number and Serial Numbers and save. Entering the full qty will automatically set the Complete flag.
Select Request Move check box to create MFG-xxx transaction type Material Queue record .
REPORT QUANTITY option opens Report Quantity entry form where partial completed quantities can be entered against ongoing production activity.
...
Start Setup is used to enter job operation information for a setup activity. Note.
Note: You must be “Clocked In” to access this menu item, if not clocked in, you will be automatically redirected to the Clock In form.
Processing Steps:
Enter the job number, assembly sequence and operation sequence.
If the number and sequences are valid, it will automatically load the job details. You can override the Resource group and/or Resource.
Click START SETUP to start the setup and add it to the work queue. Or you can add more setup operations to the work queue.
...
Start Rework is used to start rework activity on a job.
Note: You must be “Clocked In” to access this menu item, if not clocked in, you will be automatically redirected to the Clock In form.
Processing Steps:
Enter the job number, assembly sequence and operation sequence.
If the number and sequences are valid, it will automatically load the job details.
Click START REWORK to start the rework and add it to the work queue.
...
Started Activities
(Requires the 'Job Management' module)
Use Work Queue Started Activities to list job operations scheduled in each resource group. This queue informs the shop employees of the operations to perform and the order of operations according to the schedule. To start direct labor entry, the employee selects a job from the list
Work Queue Started Activities also provides provide quick access to other information useful to both the employee and supervisory personnel, such as a picture of the part, extended operation, and job description. The work queue Started Activities is an extended Priority Dispatch report online that creates a paperless shop floor
...
Click START ACTIVITY and then select an Activity Type or
Select a task (add filter criteria if required)
Select action END ACTIVITY or REPORT QUANTITY
Enter details
Click END ACTIVITY or REPORT QUANTITY
...